Quantitative Aptitude · Time and Work
Basics- Concepts, Formulas and Key Points
Explanation
🟠 1. BASIC CONCEPT
Time and Work problems are based on the relationship between:
If a person completes a work in days, then the work done by that person in 1 day is:
If a person completes a work in 10 days:
🟠 2. BASIC WORK FORMULA
Therefore:
🟠 3. ONE DAY'S WORK
If A can complete a work in days:
If B can complete the same work in days:
🟠 4. WORK DONE TOGETHER
If A completes a work in days and B completes it in days, their combined one-day work is:
Therefore, time taken together is:
Simplifying:
🟠 5. THREE PEOPLE WORKING TOGETHER
If A, B and C complete the work individually in , and days:
Therefore:
🟠 6. EFFICIENCY
Efficiency means the amount of work completed per unit of time.
For the same amount of work:
🟠 7. EFFICIENCY AND TIME RELATION
If A and B have efficiencies in the ratio:
Then their times taken to complete the same work are in the inverse ratio:
🟠 8. WORK RATIO
If A and B work for the same amount of time and their efficiencies are in the ratio:
Then the work done is also in the ratio:
🟠 9. WORK DONE IN GIVEN DAYS
If a person can complete a work in days, then work completed in days is:
of the total work.
🟠 10. REMAINING WORK
If a person has completed of a work, then the remaining work is:
🟠 11. WORK AND WAGES
If workers have different efficiencies, wages should be divided according to the work done.
If the workers work for the same time:
🟠 12. MEN AND DAYS
If the amount of work is fixed:
Therefore:
More men require fewer days.
Fewer men require more days.
🟠 13. MEN, DAYS AND HOURS
If the number of working hours per day also changes:
where:
🟠 14. MEN, DAYS AND EFFICIENCY
If efficiency also changes:
This is useful when workers have different efficiencies.
🟠 15. WORK AND TIME
For the same amount of work:
If efficiency increases, time decreases.
If efficiency decreases, time increases.
🟠 16. A WORKS ALONE AND B JOINS LATER
If A completes of the work before B joins, then remaining work is:
Then calculate the combined rate of A and B for the remaining work.
🟠 17. A LEAVES BEFORE COMPLETION
If A and B work together initially and A leaves after a certain number of days:
Then:
The remaining work is completed by the remaining worker.
🟠 18. ALTERNATE WORKING
If A and B work on alternate days:
For two-day cycles:
🟠 19. PIPES AND CISTERNS
The same Time and Work concept applies to pipes.
If a pipe fills a tank in hours:
If another pipe empties the tank in hours:
Net rate:
🟠 20. FILLING PIPES TOGETHER
If two pipes fill a tank in and hours:
Therefore:
🟠 21. FILLING AND EMPTYING PIPE TOGETHER
If a pipe fills a tank in hours and another empties it in hours:
Therefore:
🟠 22. LCM METHOD
A convenient method for solving Time and Work problems is to assume the total work as the LCM of the individual times.
For example, if A takes 10 days and B takes 15 days:
Assume:
A's efficiency:
B's efficiency:
🟠 23. IMPORTANT KEY POINTS
• Always convert the given information into work done per unit time.
• If a person takes more days, their efficiency is lower.
• If a person takes fewer days, their efficiency is higher.
• For people working together, add their individual work rates.
• For a person leaving the work, calculate the work completed before leaving and then calculate the remaining work.
• For fixed work:
• When hours per day are included:
• When efficiency is included:
• Pipes filling a tank are treated as positive work.
• Pipes emptying a tank are treated as negative work.
• In alternate-day problems, calculate the work completed in one complete cycle.
• LCM method often makes calculations easier.
Example
🟢 EXAMPLE 1: ONE DAY'S WORK
QUESTION:
A can complete a work in 10 days. What part of the work does A complete in one day?
SOLUTION:
ANSWER:
🟢 EXAMPLE 2: TWO PEOPLE WORKING TOGETHER
QUESTION:
A can complete a work in 10 days and B can complete it in 15 days. How many days will they take together?
SOLUTION:
A's one-day work:
B's one-day work:
Combined work:
Taking LCM:
Therefore:
ANSWER:
🟢 EXAMPLE 3: THREE PEOPLE WORKING TOGETHER
QUESTION:
A can complete a work in 12 days, B in 18 days and C in 36 days. Find the time taken by all three together.
SOLUTION:
Combined one-day work:
Taking LCM 36:
Therefore:
ANSWER:
🟢 EXAMPLE 4: EFFICIENCY RATIO
QUESTION:
A is twice as efficient as B. If B completes a work in 20 days, how many days will A take?
SOLUTION:
Since A is twice as efficient:
Time is inversely proportional to efficiency.
Therefore:
Hence:
ANSWER:
🟢 EXAMPLE 5: FINDING WORK DONE
QUESTION:
A can complete a work in 20 days. What fraction of the work will A complete in 8 days?
SOLUTION:
One-day work:
Work done in 8 days:
ANSWER:
🟢 EXAMPLE 6: REMAINING WORK
QUESTION:
A completes of a work. What fraction of the work remains?
SOLUTION:
ANSWER:
🟢 EXAMPLE 7: A WORKS ALONE, THEN B JOINS
QUESTION:
A can complete a work in 12 days. A works alone for 4 days, after which B joins A. If B alone can complete the work in 24 days, how many more days are required to finish the work?
SOLUTION:
A's one-day work:
Work done by A in 4 days:
Remaining work:
B's one-day work:
Combined one-day work:
Time required:
ANSWER:
🟢 EXAMPLE 8: A LEAVES AFTER WORKING TOGETHER
QUESTION:
A and B can complete a work in 12 and 18 days respectively. They work together for 3 days, after which A leaves. How many more days will B take to finish the remaining work?
SOLUTION:
Combined one-day work:
Work completed in 3 days:
Remaining work:
B's one-day work:
Time required:
ANSWER:
🟢 EXAMPLE 9: MEN AND DAYS
QUESTION:
12 men can complete a work in 15 days. How many days will 20 men take to complete the same work?
SOLUTION:
For fixed work:
ANSWER:
🟢 EXAMPLE 10: MEN AND HOURS
QUESTION:
10 men working 8 hours per day can complete a work in 12 days. How many days will 16 men working 6 hours per day take?
SOLUTION:
Using:
ANSWER:
🟢 EXAMPLE 11: EFFICIENCY AND MEN
QUESTION:
8 men can complete a work in 15 days. If each new worker is 25% more efficient than an original worker, how many days will 10 such workers take?
SOLUTION:
Efficiency of each new worker:
Thus:
Equivalent efficiency of 10 new workers compared with original workers:
Using:
where effective workers are 8 and 12.5:
ANSWER:
🟢 EXAMPLE 12: WAGES
QUESTION:
A and B complete a work together and receive ₹1,200. A does of the work and B does . Find their respective shares.
SOLUTION:
Wages are proportional to work done.
A's share:
B's share:
ANSWER:
🟢 EXAMPLE 13: ALTERNATE DAYS
QUESTION:
A can complete a work in 10 days and B can complete it in 15 days. They work on alternate days, starting with A. How many days will they take to complete the work?
SOLUTION:
A's one-day work:
B's one-day work:
Work completed in 2 days:
In 10 days, there are 5 complete cycles.
Work completed:
Remaining work:
A works on the 11th day:
Remaining after A:
B completes this remaining work in one day.
Therefore:
ANSWER:
🟢 EXAMPLE 14: PIPES FILLING TOGETHER
QUESTION:
A pipe can fill a tank in 12 hours and another pipe can fill it in 18 hours. How long will they take together?
SOLUTION:
First pipe's rate:
Second pipe's rate:
Combined rate:
Therefore:
ANSWER:
🟢 EXAMPLE 15: FILLING AND EMPTYING PIPE
QUESTION:
A pipe fills a tank in 10 hours while another pipe empties it in 15 hours. If both are opened together, how long will it take to fill the tank?
SOLUTION:
Filling rate:
Emptying rate:
Net rate:
Therefore:
ANSWER:
🟢 EXAMPLE 16: TWO WORKERS WITH DIFFERENT EFFICIENCIES
QUESTION:
A is 50% more efficient than B. If B can complete a work in 18 days, how many days will A take?
SOLUTION:
Let B's efficiency be:
A's efficiency:
Efficiency ratio:
Time ratio is inverse:
Therefore:
ANSWER:
🟢 EXAMPLE 17: FINDING ONE WORKER'S TIME
QUESTION:
A and B together can complete a work in 8 days. A alone can complete it in 12 days. How many days will B alone take?
SOLUTION:
Combined one-day work:
A's one-day work:
B's one-day work:
Therefore:
ANSWER:
🟢 EXAMPLE 18: PART OF WORK COMPLETED
QUESTION:
A can complete a work in 16 days. B can complete the same work in 24 days. They work together for 4 days. What fraction of the work remains?
SOLUTION:
Combined one-day work:
Work completed in 4 days:
Remaining work:
ANSWER:
🟢 EXAMPLE 19: WORK AND EFFICIENCY
QUESTION:
A is 25% more efficient than B. If B takes 20 days to complete a work, find the time taken by A.
SOLUTION:
B's efficiency:
A's efficiency:
Therefore:
Time ratio:
Therefore:
ANSWER:
🟢 EXAMPLE 20: MEN, DAYS AND HOURS
QUESTION:
15 men working 6 hours per day complete a work in 20 days. How many men are required to complete the same work in 15 days by working 8 hours per day?
SOLUTION:
Using:
ANSWER: